We understand that a small parcel of land, (approximately 2 acres), has now been purchased by Tipperary Co. Council, from the Ryan Family, to construct the long awaited inner relief road for Thurles town, same planned to join the N62 at Slievenamon Road, Thurles, exiting northwards, unto the Mill Road.
An Bord Pleanala granted permission for the development of this Thurles inner relief road 10 years ago, in July 2014. Same was granted resulting in the annulation and total destruction of the historic Great Famine Double Ditch, which we here at Thurles.Info fought so hard to retain, while local Thurles press and Thurles local radio remained totally silent on the issue.
Late last year the acquisition 4.5 acres of land had been sought in ongoing discussions, however up until recently, no land purchase to provide for such a relief road had been agreed despite the destruction of Thurles history undertaken by Tipperary Co. Council, aided by Thurles local councillors.
In Tipperary Co. Councils Management report of February 2023 (See last item on bottom of page 9), Tipperary Council Council state that the Thurles Inner Relief Road scheme would take approximately 3 years to complete. A consultant was expected to have the tender documentation prepared by Q4 2023, so that a works contractor could be appointed by Q1 2024, with the next stage being to “Secure funding to deliver the Inner Relief Road project and finalise land acquisition.”
So far as the public are aware to date, only €75,000 had been allocated to this project, under the Regional and Local Roads Programme.
However, (SEE HERE), Fianna Fáil TD Mr Jackie Cahill stated, (video of October 2021 last), quote “I am delighted to have secured funding for this inner relief road”.
A contract for the purchase is expected to be officially signed on Friday next. Same will also now allow for the construction of a footpath on the Mill Road, previously put on hold by the failure to acquire the same stated property.