EPA – Pace At Which Improvements In Waste Water Treatment Is Being Delivered Is Too slow.

Unacceptable delays and the pace at which essential improvements in waste water treatment are being delivered is too slow, says EPA.

  • 34 towns and villages release raw sewage into the environment every day, and a third of these will continue to do so after 2024.
  • 12 large towns and cities did not meet waste water treatment standards set to protect our environment. These areas generate half of Ireland’s waste water.
  • Ireland will need substantial and sustained investment to bring public waste water treatment up to standard.

The EPA report on Urban Waste Water Treatment in 2020, released today, shows that the pace at which essential improvements in waste water treatment are being delivered is too slow.

Irish Water is making progress in resolving environmental issues and the number of priority areas has reduced from 148 to 97 over the past four years. However, there is still a long way to go to bring all deficient treatment systems up to standard.

There have been further delays in providing treatment for many of the 34 towns and villages discharging raw sewage, and as a result over one third of these areas will not receive treatment until after 2024.

River Suir, Thurles, Co. Tipperary

Investment in waste water infrastructure is bringing environmental benefits to some areas. The number of large towns and cities failing to meet EU treatment standards is down from 28 in 2017 to 12 in 2020. However, the final deadline for all large urban areas to meet these treatment standards was 2005.

Commenting on the report, Dr Tom Ryan, Director of the EPA’s Office of Environmental Enforcement said: “It is unacceptable that 15 years after the final deadline to comply, half of Ireland’s urban waste water is still not treated to the basic EU standards. There are repeated delays in providing proper treatment at many areas, and this continues to put our environment and people’s health at risk. It is clear that Ireland will still need substantial investment over many years to bring our public waste water treatment plants and public sewers up to standard. Irish Water must deliver the essential infrastructure in as timely a manner as possible and resolve the underlying causes for the delays in upgrading treatment systems.”

The EPA report identifies the priority areas where improvements are most urgently needed and will deliver the greatest environmental benefits.

Mr Noel Byrne, EPA Programme Manager said: “While we are seeing progress at some areas, it is very concerning that Irish Water still has no clear action plans setting out when and how it will improve treatment at many of the priority areas where waste water is threatening the quality of our rivers and coastal waters. It is essential that Irish Water improves treatment to resolve the environmental issues highlighted by the EPA and provides clear, site specific action plans and time frames to carry out this work.”

The report contains key actions recommended for Irish Water as follows:

  • Direct resources to the priority areas and ensure there is a clear plan and time frame to resolve the environmental issues at each area.
  • Resolve the underlying causes for delays in upgrading treatment systems and deliver upgrade works in as timely a manner as possible.
  • Complete the impact assessments for shellfish waters and address the information shortfalls on the condition and performance of collecting systems.

The report is now available on the EPA Website.

Facebooktwitterlinkedinmail

Leave a Reply

You can use these HTML tags

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

  

  

  

This site uses Akismet to reduce spam. Learn how your comment data is processed.