Progress Report On Templemore Flood Relief Scheme – Michael Lowry T.D.
Independent Deputy Mr Michael Lowry has today confirmed that “further to a number of meetings with Minister Boxer Moran concerning my desire to ensure that the Templemore Flood Relief Scheme is advanced as quickly as possible I have been informed by the Office of Public Works (OPW) that the main scheme is progressing. Also an engineering solution has been identified and agreed with the engineering staff of Tipperary County Council, to resolve the flooding problems at Blackcastle Road and Priory Demesne which have had a huge negative impact on residents of that area”.
Deputy Lowry stated:
• The Templemore flood relief scheme commenced construction in June 2017, being carried out directly by OPW staff, with specialist contractors engaged as necessary.
• The OPW have 10 directly employed staff committed to the scheme, active on 5 different sites across Templemore. If necessary an additional crew will be assigned to the site to keep within the completion time scale.
• Work has been progressing in several areas of Templemore, with 3 field bridges now complete, and 2 further bridges under construction.
• Over 130m of new channel has been excavated, with 320m of existing river downstream from the town having been widened.
• A structure on the Richmond road has been demolished successfully, and works on utilities diversions are also ongoing.
• OPW staff have been in ongoing discussions with landowners in the area, as well as with concerned bodies such as Inland Fisheries Ireland (IFI) and the local angling club.
• It is envisaged that, barring significant delays, works should be completed towards the end of 2019.
Deputy Lowry stated that he is very grateful for the support of Minister Boxer Moran and the commitment of the OPW to this project. “I am satisfied that all of the disappointments and setbacks of the past have been overcome with this scheme coming to fruition next year”, Deputy Lowry concluded.